Oracle ASCP Programs


  • Push Plan Information

This concurrent process deletes an entire plan on the source instance and then replaces it with a copy of the current plan from the destination instance.

Prerequisites: A plan that has been run successfully.

Parameters:
Instance
Plan Type
Plan Name
Buy Orders Only: The default is No.
Demand: If you select Yes, the process purges and re-populates table 
mrp_gross_requirements with requirements from the plan. If you select No, the process leaves the data in table mrp_gross_requirements. The default is Yes.
Organization Code: The list of values contains the planned organizations of the selected
plan.
Planner: The list of values contains the planners of the items planned in the selected 
plan.
Category: The list of values contains the categories in the default planning category set.
Item: You can select a specific item. If you leave this parameter blank, the process 
pushes information for all items planned in the selected plan.
Supplier: The list of values contains the suppliers in the plan assignment set. You can 
select a value for this parameter only if:
• Buy Orders Only is Yes
• Demand is No
Supplier Site: The list of values contains the supplier sites in the plan assignment set. 
You can select a value for this parameter only if:
• Supplier has a value
• Demand is No
Horizon Start Date: The earliest Suggested Due Date for which you want plan 
information pushed. If you leave this parameter blank, the process begins with the plan 
start date.
Horizon End Date: The latest Suggested Due Date for which you want plan information
pushed. The default is one year from today. If you leave this parameter blank, the 
process ends with the plan horizon.

Example 1: Minimal Criteria
Settings:
• Buy Orders Only: No
• Demand: Yes
• Organization, Planner, Category, Item, Supplier, Supplier Site, Horizon Start Date, 
Horizon End Date:
The process:
• All supplies and demands from the selected plan in the source instance are deleted.
• All supplies and demands from the selected plan in the destination instance are 
copied to the source instance

 

Tuesday, February 11, 2014

Collaborative Planning

Oracle Collaborative Planning (CP) is part of Advanced Planning Suite (APS), just like ASCP, Demantra etc.

Helps you collaborate securely with your trading partners, reduce planning cycle time, and identify and react quickly to supply chain exceptions. Oracle Collaborative Planning enables you to increase forecast accuracy, implement vendor managed and consigned inventory processes, increase global supply visibility, reduce supply shortages, and lower expediting cost.

Vendor Managed Inventory (VMI)


Vendor Managed Inventory (VMI) is a streamlined approach to inventory management and order fulfillmentInstead of sending purchase orders, customers electronically send daily demand information to the supplier. The supplier generates replenishment orders for the customer based on this demand information. The process is guided by mutually agreed upon objectives for the customer's inventory levels, fill rates, and transaction costs.

In the transformation from a 'push' approach to supply chain management to a demand-driven 'pull' approach, unfiltered demand signals are a critical element. VMI provides those signals.

Vendor Managed Inventory with suppliers (supplier-facing VMI) enables you to share on-hand, supplies, and forecast information with suppliers, transfer replenishment responsibility to suppliers, and automate replenishment processes.


VMI
Note that suppliers who enter into VMI recognize the need to maintain a high level of trust with their customers - a transparent system makes it clear to both parties if performance criteria is not being met.